PROGRESS OF CONSTRUCTION OF HORIZON PODOL BUSINESS CENTER

Дата: 
26.03.09

Erection of Building 1 is over, finishing operations were started, including laying marble and elevation tiles. The elevation will be finished in the classical style, in the spirit of the early 20th century, with special elevation tiles ordered for that purpose. The photograph below shows preparation of the building for elevation finishing. Installation of engineering networks is in progress, too.

In Building 2, installation of a monolithic ferroconcrete base slab is nearing completion, installation of pylons and arrangement of the entrance lobby are underway.

Превью: 
<p class="bodytext">Erection of Building 1 is over, finishing operations were started, including laying marble and elevation tiles. The elevation will be finished in the classical style</p>
Вес: 
40
All news

New tenant

November 2018

Forever living products company has moved to Horizon Podol at the beginning of November. ...??


PROGRESS OF CONSTRUCTION AT NABEREZHNO-KHRESHCHATYTSKA

November 2013

There is no construction works of a 9-storeyed building at the moment, 5-storeyed building is fully occupied....??


PROGRESS OF CONSTRUCTION AT NABEREZHNO-KHRESHCHATYTSKA, 9, February 2010

19.02.10

This month, BASF company moved to Building 1 – a lease agreement covering floors 1, 2, 3 and 4 was signed. Therefore, BASF, together with EBEWE company accommodated on the 5th floor, leased 100% of space in that building....??


PROGRESS OF CONSTRUCTION AT NABEREZHNO-KHRESHCHATYTSKA, 9

11.12.09

Last month we signed Tenancy Contract with EBEWE pharma company. Now they occupy 5th floor of the building....??


PROGRESS OF CONSTRUCTION AT NABEREZHNO-KHRESHCHATYTSKA, 9

08.10.09

5-storeyed building: Readiness – 95%. For façade decoration, only installation of ceramic granite boards along the perimeter of the 1st floor remained. Internal finishing completed at: stairway, elevator lobby, windows facing the Dnieper...??


PROGRESS OF CONSTRUCTION OF BUILDING, LOCATED AT 9 NABEREZHNO-KHRESHCHATYTSKA STR.

14.08.09

Five-storey building: Roof construction has been completed. Front elevation has been warmed, at the moment the front elevation décor elements are being mounted and the front elevation is being pained Inside finishing works have been mostly...??


CONSTRUCTION PROGRESS OF HORIZON PODOL BUSINESS CENTER – LOCATED AT 9 NABEREZHNO-KHRESHCHATYTSKA STR.

06.07.09

Five-storey building: - presently the works for façade heat insulation are being finished, then the façade will be covered with the stucco and will be painted. - metal tiling is being installed on the roof, in the photo below one of the towers of...??


CITY PLANNING COUNCIL

16.04.09

April 16, 2009 a City Planning Council took place, where the construction of 2 office projects was considered: 9, Naberezhno-Kreschatitskaya Str. ("Horizon Podol Business Center") and 4, Gospitalnaya Str. After...??


PROGRESS OF CONSTRUCTION OF HORIZON PODOL BUSINESS CENTER

26.03.09

Erection of Building 1 is over, finishing operations were started, including laying marble and elevation tiles. The elevation will be finished in the classical style...??


2009-2013 © PJSC ISA Prime Developments
Ukraine, 03680, Kyiv, N.Grinchenko st, 4 HORIZON PARK BUSINESS CENTER
phone: (044) 490-69-70, 490-69-64, 496-90-52; fax (044) 496-37-57
e-mail: svetlana@nhps.kiev.ua, reservation@nhps.kiev.uа