Five-storey building:
Roof construction has been completed.
Front elevation has been warmed, at the moment the front elevation décor elements are being mounted and the front elevation is being pained.
Inside finishing works have been mostly completed - remaining are the works to install lamps and cover floor (these will be fulfilled with regard to the would-be leaseholder’s wishes).
Air-conditioning and ventilation system has been completely mounted.
Double-glass glass-packs have been installed in all premises.
Elevator by OTIS Company has been installed.
All engineering systems have been installed.
Nine-storey building:
At this stage, the installation of a concrete floor on the 2nd storey is being completed.
Forever living products company has moved to Horizon Podol at the beginning of November. ...??
There is no construction works of a 9-storeyed building at the moment, 5-storeyed building is fully occupied....??
This month, BASF company moved to Building 1 – a lease agreement covering floors 1, 2, 3 and 4 was signed. Therefore, BASF, together with EBEWE company accommodated on the 5th floor, leased 100% of space in that building....??
Last month we signed Tenancy Contract with EBEWE pharma company. Now they occupy 5th floor of the building....??
5-storeyed building: Readiness – 95%. For façade decoration, only installation of ceramic granite boards along the perimeter of the 1st floor remained. Internal finishing completed at: stairway, elevator lobby, windows facing the Dnieper...??
Five-storey building: Roof construction has been completed. Front elevation has been warmed, at the moment the front elevation décor elements are being mounted and the front elevation is being pained Inside finishing works have been mostly...??
Five-storey building: - presently the works for façade heat insulation are being finished, then the façade will be covered with the stucco and will be painted. - metal tiling is being installed on the roof, in the photo below one of the towers of...??
April 16, 2009 a City Planning Council took place, where the construction of 2 office projects was considered: 9, Naberezhno-Kreschatitskaya Str. ("Horizon Podol Business Center") and 4, Gospitalnaya Str. After...??
Erection of Building 1 is over, finishing operations were started, including laying marble and elevation tiles. The elevation will be finished in the classical style...??